Myanmar-Laos Bridge is being erected smoothly under the guidance of technical team of Harzone. The erection begins with the Myanmar side. The first span is erected by means of temporary support pier. It is estimated to cost about three months in completing the erection of the first span. Then, the cantilever erection means will be adopted to finish the erection of the second and third span. The mast bridge erector and the tower with suspended cable will be installed after the first span is completed.