At 8:00am on November 16th, 2013, completion ceremony of temporary steel trestle of Chibi 2nd Lushui Bridge was held on the beautiful Chibi Lushui riverside.
Temporary cross-river passage of Chibi 2nd Lushui Bridge is 180m long and 11m wide. The passage adopts deck Bailey bridge structure and design wheel load of is 80 tons. This project is the first cooperation project for the Company to provide emergency traffic plan for municipal building of Chibi. This project was started in August 2013, installation and erection was completed at the end of September, and carrying test of the bridge was completed in October. In the test by a third party professional testing organization, all indicators of the bridge have met design requirements.